WORK will continue Transurban Queensland’s new schedule of Mount Lindesay Highway works which progress the $512 million Logan Enhancement Project at Parkinson.
NORTHBOUND
Sunday marks the opening of the newly constructed Mount Lindesay Highway northbound to Logan Motorway westbound on-ramp and permanent closing of the old ramp. Final works will be completed between Saturday June 2 from 7pm and Sunday June 3 at 8am.
The works will close the the existing Logan Motorway westbound on-ramp with a detour in place and single lane closures on the Mount Lindesay HIghway northbound.
A TQ spokesperson said when work concluded, traffic would switch permanently on to the new Mount Lindesay Highway northbound to the Logan Motorway westbound on-ramp.
Motorists could expect:
- workers, vehicles and equipment, road construction and resurfacing, road pavement profilers, compaction rollers, body trucks, line marking and use of hand tools, barrier relocation and installation of new signage.Ttraffic control and reduced speeds to keep motorists and workers safe
- noisy machinery
- in the case of bad weather or delays, work will be postponed to the next available shift.
The spokesperson said the works were scheduled to minimise impacts on the community and motorists.
“We thank you in advance for your patience during these works while the new on-ramp opens and the old on-ramp closes,” the spokesperson said.
TQ’s Logan Enhancement Project includes:
- upgrades to parts of the Logan and Gateway Extension motorways, improving key congestion hot spots on Logan Motorway, Mount Lindesay Highway, Beaudesert Road interchange and the Wembley Road Logan Motorway interchange and constructing new south-facing ramps on the Gateway Extension Motorway at Compton Road.
Major construction is underway with the project anticipated to be completed in 2019.
SOUTHBOUND
SATURDAY June 9 will mark the opening of the newly constructed Beaudesert Road southbound on-ramp to Logan Motorway eastbound at Parkinson, and permanent closing off the old on-ramp.
The traffic switch will involve completing final works to open the new ramp to traffic. Key dates include:
- Stage 1 nightworks from Monday, June 4, 7pm to Tuesday, June 5, 8pm to realign the Logan Motorway eastbound traffic into the existing median east of Beaudesert Road.
- Stage 2 nightworks from Saturday, June 9, 7pm to Sunday, June 10, 5am fully the existing eastbound on-ramp with a detour in place
- single lane closures on Beaudesert Road southbound, Logan Motorway eastbound service road closure including detour for Logan Motorway eastbound on-ramp traffic from Mount Lindesay Highway northbound
- single lane closures of the Logan Motorway eastbound.
- when work concludes, traffic will be switched permanently onto the new Beaudesert Road southbound to Logan Motorway eastbound on-ramp.
The first new off-ramp constructed as part of Transurban Queensland’s $512 million Logan Enhancement Project, opening the Logan Motorway westbound off-ramp to Mount Lindesay Highway southbound was a project milestone was completed recently and opened to traffic.
TQ group executive Sue Johnson said opening the Logan Motorway westbound off-ramp to Mount Lindesay Highway southbound was a project milestone.
“I have been really impressed with the project’s pace since major construction started in mid-2017. It’s great to see the benefits starting to be realised with the opening of this new off-ramp,” Ms Johnson said.
“The project is delivering more than roads.”
In July, work starts on a new dedicated 2km shared bike and pedestrian path over Logan Motorway at the Mt Lindesay Highway and Beaudesert Road interchange, providing an important connection between Illaweena Street to the north and Acacia Street to the south.
“Delivering this missing link between two existing shared paths is another terrific example of how the Logan Enhancement Project benefits all road users.”
TQ general manager delivery Ian Sinclair said construction was pushing ahead despite a wet first quarter of the year.
“The community will soon see several new ramps open to traffic including the Mount Lindesay Highway northbound on-ramp to the Logan Motorway westbound and the new Logan Motorway eastbound on-ramp from Beaudesert Road southbound,” Mr Sinclair said.
“Construction is about 30 per cent of the way there with more than a million construction hours worked to date.
“On average, 600 people sign on to work each day, dedicated to getting on with the job of upgrading our network to provide better roads for our customers.”
Major construction is underway with the project anticipated to be completed in 2019.
TQ recommends motorists keep updated about traffic changes during construction and plan ahead.
For more information about upcoming traffic changes, view the road users page on the project website.
Traffic information will also be posted on the Queensland Traffic website and provided to the 131940 call centre.
For more information about construction activities associated with the Logan Enhancement Project, please visit the project website at www.loganenhancementproject.com.au, follow the project on Facebook at facebook.com/LoganEP/
For more information about the project or to speak with a member of the community relations team phone 1800 195 308 toll free 24 hours or email contactus@loganenhancementproject.com.au